Question:
Using the same data from Problem 23, and the same contract type, how much will the contractor be reimbursed if the cost of performing the work is $105,000?
Data from problem 23
An FPIF contract has the following characteristics:
Sharing ratio: 70/30
Target cost: $100,000
Target fee: $8,000
Price ceiling: $110,000
A. $105,000
B. $106,500
C. $110,000
D. $111,500