Using the same data from Problem 23, and the same contract type, how much will the contractor

Question:

Using the same data from Problem 23, and the same contract type, how much will the contractor be reimbursed if the cost of performing the work is $102,000?

Data from problem 23

An FPIF contract has the following characteristics:
Sharing ratio: 70/30
Target cost: $100,000
Target fee: $8,000
Price ceiling: $110,000 


A. $104,000
B. $107,400
C. $109,400
D. $110,000

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: