Using the same data from Problem 20, and the same contract type, how much will the contractor

Question:

Using the same data from Problem 20, and the same contract type, how much will the contractor be reimbursed if the cost of performing the work is $85,000?

Data from problem 20

A cost-plus-incentive-fee contract has the following characteristics:
Sharing ratio: 80/20
Target cost: $100,000
Target fee: $12,000
Maximum fee: $14,000
Minimum fee: $9,000 


A. $97,000
B. $99,000
C. $112,000
D. $114,000