Responsibility Estim. Duration Earliest Latest Total Slack Activity start Finish start Finish Fill in the following table by calculating the ES, EF, LS, and LF
Responsibility | Estim. Duration | Earliest | Latest | Total Slack | ||
Activity | start | Finish | start | Finish |
Fill in the following table by calculating the ES, EF, LS, and LF times (if the required completion time is 60 days) and the slack for each activity in the figure below.
Step by Step Solution
There are 3 Steps involved in it
Step: 1