Review the Network Diagram given below. Based on the diagram, what day(s) should you schedule for Task D? Why? Duration Predecessor D1 D2 D3 D4
Review the Network Diagram given below. Based on the diagram, what day(s) should you schedule for Task D? Why? Duration Predecessor D1 D2 D3 D4 D5 D6 D7 D8 D9 D10 Task A 1 1 day n/a 2 Task B 2 days 1 Task C 4 days 1 3 Task D 4 1 day 2,3