Rita is managing a project with an estimated budget at completion of $500,000. Her team should have completed 40% of the work by now according
Rita is managing a project with an estimated budget at completion of $500,000. Her team should have completed 40% of the work by now according to the schedule. However, at the last status meeting, the team reported that 35% of the work has actually been completed. The team has already spent $225,000 so far on the project. As a supervisor to Rita's project how would you BEST describe the project? Question 2 options: The project is behind schedule and within its budget The project is behind schedule and over its budget The project is behind schedule and over its budget The project is behind schedule and positive variance The project is ahead of schedule and within its budget The project is ahead of schedule and over its budget
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started