Rita was recently named the risk manager of ACE Corporation. She has decided to create a risk management program which considers all of the risks
Rita was recently named the risk manager of ACE Corporation. She has decided to create a risk management program which considers all of the risks faced by the ACE Corporation pure, speculative, operational, and strategic in a single risk management program. Such a program is called
fundamental risk management program
financial risk management program
consequential risk management program
enterprise risk management program