rktec Manufacturing must choose between the following two capacity options. LOADING... Click the icon to view the options table. Part 2 a . What would

rktec Manufacturing must choose between the following two capacity options.
LOADING... Click the icon to view the options table.
Part 2
a. What would the cost be for each option if the demand level is 30 comma 000 units per year? If it is 90 comma 000 units per year?
Calculate the total costs for each option if the demand level is 30 comma 000 units per year (enter your responses as whole numbers).
Part 3
Demand(units per year)
Total cost(per year)
Option 1
30 comma 000
$
enter your response here
Option 2
30 comma 000
$
enter your response here
Part 4
Find the total costs for each option if the demand level is 90 comma 000 units per year (enter your responses as whole numbers).
Part 5
Demand(units per year)
Total cost(per year)
Option 1
90 comma 000
$
enter your response here
Option 2
90 comma 000
$
enter your response here
Part 6
b. In general, which option do you think would be better as volume levels increase? As they decrease?
A.
As volume levels increase, Option 2 will be better, since the variable cost is lower. As volumes decrease, Option 1 will be better, as the fixed cost is lower.
B.
As volume levels increase, Option 1 will be better, since the variable cost is lower. As volumes decrease, Option 2 will be better, as the fixed cost is lower.
C.
As volume levels increase, Option 1 will be better, since the fixed cost is lower. As volumes decrease, Option 1 will be better, as the variable cost is lower.
D.
As volume levels increase, Option 2 will be better, since the fixed cost is lower. As volumes decrease, Option 2 will be better, as the variable cost is lower.
Part 7
c. The indifference point is
enter your response here units. (Enter your response rounded to the nearest whole number.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project management

Authors: Harvey maylor

4th Edition

027370432X, 978-0273704324

More Books

Students also viewed these General Management questions

Question

Calculate different elasticities price, income and cross?

Answered: 1 week ago