Question
Rob, the project manager of Berwanger, Inc. has been executing a project. On July 30, 2012 the project is 60% completed and he needs help
Rob, the project manager of Berwanger, Inc. has been executing a project. On July 30, 2012 the project is 60% completed and he needs help with the following measurements:
What is the cost variance?
What is the schedule variance?
What is the cost performance index?
What is the schedule performance index?
What is the estimate at completion?
What is the estimate to complete?
What is the variance at completion?
What is the resource utilization efficiency?
What is the resource utilization index?
What is the percent complete?
What is the percent spent?
What is the status of the project?
Completion Date | PV ($M) | EV ($M) | AC ($M) | Activity |
Jan 31 | 8 | 8 | 13 | A |
Feb 27 | 4 | 3 | 6 | B |
March 30 | 6 | 8 | 4 | C |
Apr 30 | 15 | 12 | 10 | D |
May 30 | 20 | 20 | 25 | E |
June 30 | 9 | 8 | 4 | F |
July 30 | 20 | 14 | 21 | G |
August 30 | 15 | 0 | 0 | H |
Sept 30 | 25 | 0 | 0 | I |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started