Robby is considering a capital budgeting project that has an expected return of 35% and a standard deviation of 25%. What is the project's coefficient
Robby is considering a capital budgeting project that has an expected return of 35% and a standard deviation of 25%. What is the project's coefficient of variation? Do not round your intermediate calculations. Round the final answer to 2 decimal places. a. 0.92 b. 0.78 c. 0.71 d. 0.83 e. 0.80