Robin Construction Company began a long term contract in 2018. The contract price was $800,000. The estimated cost of the contract at the time it
Robin Construction Company began a long term contract in 2018. The contract price was $800,000. The estimated cost of the contract at the time it was begun was $500,000. The actual cost incurred in 2018 was $350,000. The contract was completed in 2019 and the cost incurred was $125,000. Under the percentage of completion method.
a. Robin should report $90,000 of income in 2018
b. Robin should report $210,000 income in 2018
c. Robin should report $300,000 income in 2018
d. Robin should report $325,000 income in 2018
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started