Question

1 Approved Answer

Robin Construction Company began a long term contract in 2018. The contract price was $800,000. The estimated cost of the contract at the time it

Robin Construction Company began a long term contract in 2018. The contract price was $800,000. The estimated cost of the contract at the time it was begun was $500,000. The actual cost incurred in 2018 was $350,000. The contract was completed in 2019 and the cost incurred was $125,000. Under the percentage of completion method.

a. Robin should report $90,000 of income in 2018

b. Robin should report $210,000 income in 2018

c. Robin should report $300,000 income in 2018

d. Robin should report $325,000 income in 2018

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting

Authors: Loren A Nikolai, D. Bazley and Jefferson P. Jones

10th Edition

324300980, 978-0324300987

More Books

Students also viewed these Accounting questions