Question
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Time (weeks) Immediate
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels.
Time (weeks) | Immediate | Time (weeks) | Immediate | ||||||||||||
Activity | a | m | b | Predecessor(s) | Activity | a | m | b | Predecessor(s) | ||||||
A | 4 | 9 | 12 | G | 2 | 3 | 4 | C, E | |||||||
B | 1 | 8 | 23 | A | H | 1 | 1 | 1 | F | ||||||
C | 9 | 14 | 18 | A | I | 7 | 7 | 7 | F | ||||||
D | 5 | 6 | 10 | A | J | 6 | 8 | 14 | D, G, H | ||||||
E | 1 | 2 | 4 | B | K | 1 | 1 | 4 | I, J | ||||||
F | 5 | 9 | 20 | C, E |
Part 2a) The expected (estimated) time for activity C is
______
weeks. (Round your response to two decimal places.)Part 3b) The variance for activity C is
______
weeks. (Round your response to two decimal places.)Part 4c) Based on the calculation of the estimated times, the critical path is _________
A - B - E - F - H - J - K
A - C - G - J - K
A - B - E - G - J - K
A - B - E - F - I - K
A - C - F - H - J - K
A - D - J - K
A - C - F - I - K
.
Part 5d) The estimated time for the critical path is
______
weeks. (Round your response to two decimal places.)Part 6e) The activity variance along the critical path is
__________
weeks. (Round your response to two decimal places.)Part 7f) Using the
standard normal table
LOADING...
,
the probability that Hopkins Hospitality will finish the project in
40
weeks or less is
__________.
(Enter as a probability and round your response to three decimal places.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started