Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. table [

Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels.
\table[[,Time (weeks),Immediate,,Time (weeks),Immediate],[Activity,a,m,b,Predecessor(s),Activity,a,m,b,Predecessor(s)],[A,6,8,12,-,G,2,3,5,C, E],[B,2,9,23,A,H,1,1,1,F],[C,9,12,16,A,I,7,7,7,F],[D,4,6,9,A,J,6,8,12,D, G, H],[E,1,3,4,B,K,1,1,4,I, J],[F,5,9,21,C, E,,,,,]]
a) The expected (estimated) time for activity C is 12.16 weeks. (Round your response to two decimal places.)
b) The variance for activity C is weeks. (Round your response to two decimal places.)
c) Based on the calculation of the estimated times, the critical path is A-B-E-F-H-J-K.
d) The estimated time for the critical path is weeks. (Round your response to two decimal places.)
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic management concepts

Authors: Fred david

13th Edition

9780136120988, 136120997, 136120989, 978-0136120995

More Books

Students also viewed these General Management questions