RossHopkins, president of HopkinsHospitality, has developed thetasks, durations, and predecessor relationships in the following table for building new motels. Time (weeks) Immediate Time (weeks) Immediate

RossHopkins, president of HopkinsHospitality, has developed thetasks, durations, and predecessor relationships in the following table for building new motels.

Time

(weeks)

Immediate

Time

(weeks)

Immediate
Activity a m b Predecessor(s) Activity a m b Predecessor(s)
A 66 99 1010 long dash G 33 33 55 C, E
B 22 88 2323 A H 11 11 11 F
C 99 1212 1616 A I 55 55 55 F
D 44 77 99 A J 44 77 1414 D, G, H
E 11 22 44 B K 11 11 44 I, J
F 66 88 2121 C, E

Part 2

a) The expected(estimated) time for activity C is

12.6712.67

weeks. (Round your response to two decimalplaces.)

Part 3

b) The variance for activity C is

1.361.36

weeks. (Round your response to two decimalplaces.)

Part 4

c) Based on the calculation of the estimatedtimes, the critical path is

A - C - F - H - J - K

.

c) The length of the path A - B - E - F - H - J - K is ______ weeks. (Round your response to two decimalplaces.)

Part 8

The length of the path A BEFIK is ______ weeks. (Round your response to two decimalplaces.)

Part 9

The length of the path ABEGJK is ________ weeks. (Round your response to two decimalplaces.)

Part 10

The length of the path ACFHJK is _______ weeks. (Round your response to two decimalplaces.)

Part 11

The length of the path ACFIK is ________ weeks. (Round your response to two decimalplaces.)

Part 12

The length of the path ACGJK is _______ weeks. (Round your response to two decimalplaces.)

Part 13

The length of the path ADJK is _________ weeks. (Round your response to two decimalplaces.)

Part 14

Based on the calculation of the estimatedtimes, the critical path is _______________________.

Part 15

d) The estimated time for the critical path is _________ weeks. (Round your response to two decimalplaces.)

Part 16

e) What is the activity variance along the criticalpath?

Part 17

The activity variance sigma Subscript p Superscript 22p along the critical path is ________ weeks.

(Round your response to two decimalplaces.)

Part 18

f) What is the probability of completion of the project before week _______?

The standard normal equation can be applied asfollows:

Z= StartFraction left parenthesis Due date minus Expected date of completion right parenthesis Over sigma Subscript p EndFraction(DuedateExpecteddateofcompletion)p, where Z is the number of standard deviations the due date or target date lies from the mean or expected date and

sigma Subscript pp is the project standard deviation.

Part 19

Compute Z.

Z= StartFraction 42 minus 43.34 Over StartRoot 24.00 EndRoot EndFraction4243.3424.00

= _________. (Round your response to two decimalplaces.)

Part 20

Using the standard normal table, the probability that Hopkins Hospitality will finish the project in

________ weeks or less is _________. (Enter as a probability and round your response to three decimalplaces.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Experiencing MIS

Authors: David M Kroenke, Randall J Boyle

7th Edition

0134402197, 9780134402192

More Books

Students also viewed these General Management questions

Question

What does the coefficient of determination measure?

Answered: 1 week ago

Question

7. How can the models we use have a detrimental effect on others?

Answered: 1 week ago