Question
Roxxon Co. wants to know how long it will take project Alpha to pay back its orginal investment. Project Alpha's expected net cash flows are
Roxxon Co. wants to know how long it will take project Alpha to pay back its orginal investment. Project Alpha's expected net cash flows are shown as follows:
Year 0 = -$600,000
Year 1 = 325,000
Year 2 = 375,000
Year 3 = 450,000
The CFO wants to know project Alpha's payback period. In order to include the time value of money, we want to know the project's discounted payback period.
Assuming that annual cash flows are received evenly throughout the year and the project's WACC is 10% what is the:
Regular payback period?
Discounted payback period?
Is the regular payback method or the discounted payback period ethod better when evaluating project Alpha?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started