Question

1 Approved Answer

Roy Creasey Enterprises, a machine shop, is planning to move to a new, larger location. The new building will be 60 feet long by 40

Roy Creasey Enterprises, a machine shop, is planning to move to a new, larger location. The new building will be 60 feet long by 40 feet wide. Creasey envisions the building as having six distinct production areas, roughly equal in size. He feels strongly about safety and intends to have marked pathways throughout the building to facilitate the movement of people and materials. See the following building schematic.

Room

1

Room

2

Room

3

Room

4

Room

5

Room

6

His foreman has completed a month-long study of the number of loads of material that have moved from one process to another in the current building. This information is contained in the flow matrix on the left below. Finally, Creasey also developed a matrix to indicate distances between the work areas shown in the building schematic, shown on the right below.

Materials

Welding

Drills

Lathes

Grinders

Benders

Materials

0

125

55

0

0

45

Welding

20

0

0

50

0

0

Drills

25

0

0

0

50

0

Lathes

0

25

0

0

20

0

Grinders

50

0

120

0

0

0

Benders

5

0

20

0

0

0

1

2

3

4

5

6

1

20

40

20

40

60

2

20

40

20

40

3

60

40

20

4

20

40

5

20

6

1) Based on the flows shown in the matrix, it is likely that the processes Drills and ____ are in rooms next to each other as they have the highest number of moves between each other.

2) Based on the flows shown in the matrix, it is likely that the processes Materials and ___ are in rooms next to each other as they have the second highest number of moves between each other.

One of the layouts that could be designed is:

Room 1 = Benders

Room 2 = Materials

Room 3 = Welding

Room 4 = Drills

Room 5 = Grinders

Room 6 = Lathes

3) The cumulative distance based on the overall movement of material between processes for this layout = ____ feet

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Energy Audit Of Building Systems An Engineering Approach

Authors: Moncef Krarti

2nd Edition

1439828717, 978-1439828717

More Books

Students also viewed these Accounting questions

Question

38. The new cell phone comes in a variety of colors.

Answered: 1 week ago