Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase
Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building: |
Title insurance | $ | 22,000 | |
Legal fees for drawing the contract | 8,000 | ||
Pro-rated property taxes for the period after acquisition | 42,000 | ||
State transfer fees | 4600 |
An independent appraisal estimated the fair values of the land and building, if purchased separately, at $4 and $1 million, respectively. Shortly after acquisition, Samtech spent $88,000 to construct a parking lot and $46,000 for landscaping. Samtech demolished the building. Demolition costs were $310,000 and the salvaged materials were sold for $9,000. In addition, Samtech spent $85,000 clearing and grading the land in preparation for the construction of a new building.
What is the initial valuation of the land?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started