Sanchez Company's output for the current period was assigned a $413,000 standard direct labor cost. The direct labor variances included a $10,325 unfavorable direct labor
Sanchez Company's output for the current period was assigned a $413,000 standard direct labor cost. The direct labor variances included a $10,325 unfavorable direct labor rate variance and a $4,130 favorable direct labor efficiency variance. What is the actual total direct labor cost for the current period? |
a$423,325.
b$419,195.
c$406,805.
d$398,545.
e$427,455.