Sandhill, Inc. began work in 2018 on a contract for $22120000. Other data are as follows: 20182019 Costs incurred to date$9480000$14400000Estimated costs to complete63200000Billings to
Sandhill, Inc. began work in 2018 on a contract for $22120000. Other data are as follows:
20182019Costs incurred to date$9480000$14400000Estimated costs to complete63200000Billings to date716000021800000Collections to date516000018400000
If Sandhill uses the percentage-of-completion method, the gross profit to be recognized in 2018 is
$4000000.
$3792000.
$5760000.
$6320000.