Santa Monica Proper Hotel project information: Original project budget: $120,000.00 Original project duration: 24 months Current project budget: Current project duration: 36 months Answer the

image text in transcribed
Santa Monica Proper Hotel project information: Original project budget: $120,000.00 Original project duration: 24 months Current project budget: Current project duration: 36 months Answer the following questions: $160,00.00 1. What is the percentage of budget overage currentlyi 2. What is the percentage of schedule overage currently? 3. If the contractor's fee (overhead and profit mark-up) for this project is 496, how much fee should they have received under the original budget? 4. How much fee will they receive under the current budget? 5. If there are 550 rooms, each selling for an average of $600.00 per night, how much revenue does the hotel owner stand to lose with the current projected schedule delay? earch

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Software Quality Assurance A Guide For Developers And Auditors

Authors: Howard T. Garst Smith

1st Edition

1574910493, 978-1574910490

More Books

Students also viewed these Accounting questions

Question

Write a letter asking them to refund your $1,500 down payment.

Answered: 1 week ago