Sasol Limited is considering one method for developing a mine containing an estimated 100,000 tons of iron ore. This method will result in the recovery

Sasol Limited is considering one method for developing a mine containing an estimated 100,000 tons of iron ore. This method will result in the recovery of 62% of the available ore deposit and will cost US$23.00 per ton of removed material.

Sasol Limited is also considering a second method of development which will recover 50% of available ore deposit. The second method will cost US$15.00 per ton of removed material.

Subsequent processing of the removed material will recover 300 pounds of metal from each ton of processed ore, and will cost US$40.00 per ton of ore processed. The recovered metal can be sold for US$0.80 per pound.

If Sasol Limited is to maximize profit, which method should Sasol Limited use for developing the mine?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting in an Economic Context

Authors: Jamie Pratt

8th Edition

9781118139424, 9781118139431, 470635290, 1118139429, 1118139437, 978-0470635292

More Books

Students also viewed these Accounting questions

Question

16. Explain the power of labels.

Answered: 1 week ago

Question

305 mg of C6H12O6 in 55.2 mL of solution whats the molarity

Answered: 1 week ago