Sasol Technologies, South Africa's second largest industrial undertaking, employs 28,000 people all over the world and is one of the market leaders in the field
Sasol Technologies, South Africa's second largest industrial undertaking, employs 28,000 people
all over the world and is one of the market leaders in the field of coal gas liquefaction for the
production of gasoline and components for the chemical industry. On a visit to the Japanese
producer, the African project division of Kuehne + Nagel inspected the two enormous reactor
components under construction (a bottom section weighing 419 tonnes and measuring
approximately 22 x 9 x 9 metres, and a 252-tonne upper section measuring 18 x 9 x 9 metres)
and examined the shipping possibilities at different ports on Japan's west coast. It soon became
clear that due to shipping capacity restraints, it was necessary to book a suitable ship as soon as
possible although shipping was not scheduled to take place until mid-2009. At the end of 2008 a
task force team was put together with members representing the customer, the maritime carrier
and the haulage company. It also included representatives of a company specializing in route
analysis and road clearance for heavy load transport, and a consultant for the calculation of the
required trailer configuration based on the maximum allowed road load of 27.5 kilonewtons. In
February 2009 the preparations were held up by an unexpected event. Without prior
announcement the Ministry of Roads and Works started to upgrade a part of the route from the
port of Richards Bay to the site. Since no alternative routes were available in South Africa, it was
decided to transport the reactor through Swaziland where a route was found which could be
suitable - if certain repairs and modifications were made. At the border with Swaziland, where
power and telephone cables had to be raised, the passage of the imposing convoy blocked the
customs post for all other traffic for no less than six hours. Further challenges were presented by
bad weather, which resulted in two days of delays, and a 13 per cent gradient for which five
additional prime movers had to be hired
Answer all the below questions base on the case study.
After four weeks of "highly eventful" overland transport, the reactor parts reached their
destination safely and on schedule - to the complete satisfaction of the customer and to the great
relief of the Kuehne + Nagel South Africa project division team. Hence, the challenges face by
the project team handling material for their importation was rigid. Discuss 5 (FIVE) challenges
and solution that the project team face while handling the shipment movement.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started