saved Saved Help Save & Exit Submit Check my work Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $208,960 Number of machine hours 53,125 Number of design hours 68,400 Number of batches Estimate Cost Driv $5,300 6,250 480 Check my work Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $208,960 Number of machine hours 53,125 Number of design hours 68,400 Number of batches Estimate Cost Driv 65,300 6,250 480 required: . Compute the activity rate for each activity. .. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Classify each activity as facility, product, batch, or unit level. Machining Design Setup Required 2 Activity cost pools Materials handling Machine maintenance $50, 160 $10,800 Cost drivers Number of material moves Number of machine hours 440 40,000 K Required: 1. Calculate Bluefield's activity rate for each cost pool. 2. Determine the amount of overhead assigned to Bluefield's products if each has the following activity demands: ces Number of material moves Number of machine hours Product A Product B 260 180 16,800 23,200 Complete this question by entering your answers in the tabs below. Required 1 Required 2 Determine the amount of overhead assigned to Bluefield's products if each has the intermediate calculations to 4 decimal places and your final answers to 2 decimal Total Overhead Assigned Product A Product B