Question

1 Approved Answer

Scale Probability Time Impact Very High > 70% > 300 days High 51-70% 91 - 300 days Medium 31-50% 30 - 90 days Low 11-30%

Scale Probability Time Impact Very High > 70% > 300 days High 51-70% 91 - 300 days Medium 31-50% 30 - 90 days Low 11-30% 8 - 29 days Very Low 1-10% 7 days Nil <1% No ChangeThe risk of a delay in approvals occurring on a project is estimated to have a "high" chance of occurrence, and a "high" impact. What is the expected average delay (in days) of this risk on the project? 2

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Organizational Behavior Integrating Individuals Groups And Organizations

Authors: Joseph E. Champoux

4th Edition

0415804647, 9780415804646

Students also viewed these General Management questions