Scenario: You are the project manager for a project to implement a childcare facility for your organizations employees. Duration Estimate Example You need to develop

Scenario: You are the project manager for a project to implement a childcare facility for your organizations employees.

Duration Estimate Example

You need to develop training materials for the childcare center staff. The training will take four days. You developed a similar training program a few months ago, but that program was two days long.

Because this new training program is relatively complex compared with the earlier one (it includes first aid, food prep, and safety training), increase the duration by 10 percent for a complexity factor.

Last Class

Effort

This Class

2 days

133 hours

4 days

Complex

13 hours

Complex

3 Demos

30 hours

5 Demos

What is the Analogous Estimate?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

What is a social class system?

Answered: 1 week ago

Question

6. Does your speech have a clear and logical structure?

Answered: 1 week ago