Scenario You recently were hired as a project manager for a company that builds and operates large shopping centers around the United States. Your company

Scenario

You recently were hired as a project manager for a company that builds and operates large shopping centers around the United States. Your company is planning a large mall in your town, and part of the town's approval process consists of a public meeting where the project will be presented to the community. You have been asked by your project sponsor to estimate the cost of that public meeting work package.

Public meetings for other shopping centers have cost approximately $30,000, and your sponsor has asked that you not exceed this amount. Your estimate must include direct labor and overhead costs (burdened rate) for each in-house staff resource. The standard hourly burdened rate for in-house staff is averaged to a flat $80.

There are five activities associated with the public meeting, and you have estimated the components of each activity in the data file, Public Meeting Estimate document.

New Shopping Center

Public Meeting Estimate

Activity Description Expense Estimates
Conduct Planning Meetings
  • Four 2-hour planning meetings are scheduled, each with 15 key team members in attendance.
  • Two of the meetings will be catered lunch meetings.
  • Internal labor: 120 hours.
  • Catered lunches: $15.00 per person.
Arrange Location
  • Research to locate a suitable facility. Rent necessary equipment.
  • Internal labor: 20 hours.
  • Facility rent: 5,000 sq. ft. at $0.40 to $0.50 each.
  • Equipment rent: 600 chairs at $0.25 to $0.40 each.
  • Equipment rent: 3 Large Monitors at $200.00 each per hour for two hours.
Arrange Staffing
  • Coordinate all staff and travel for the public meeting.
  • Internal labor: 50 hours.
  • Travel: 1 panel member from Florida at approximately $1,000.00.
  • Moderator: Standard fee of $500.00 for the 2-hour event.
  • Security: 6 guards for 4 hours at $50.00 per hour.
Publicize Event
  • Design, print, and mail 10,000 postcards.
  • Newspaper advertising.
  • Internal labor: 60 hours.
  • Postcards: Printing and postal charges at $0.20 to $0.25 each.
  • Advertising: $1,000.00 flat fee.
Hold Event
  • Requirements as needed to set up for, hold, and clean up after the event.
  • Internal labor: 35 hours.
  • Additional: 2 speakers at $50.00 each per hour for 2 hours.
  1. What technique did you use to estimate the cost of the Conduct Planning Meetings activity? Why is this technique beneficial?
  2. Which estimating technique was used for the Arrange Staffing activity?
  3. What is the degree of certainty of your cost estimate now?
  4. Do you need to take any action regarding the sponsor's target of $30,000? If so, what action should you take?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Operations and Supply Chain Management

Authors: Cecil B. Bozarth, Robert B. Handfield

5th edition

134740602, 134740912, 9780134692869 , 978-0134740607

More Books

Students also viewed these General Management questions