Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 5 C A 4 D B 3 E C ,D
Schedule the following activities using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 3
B A 5
C A 4
D B 3
E C ,D 6
F D 4
G F 3
H E,G 5
b.What is the critical path?
- A-C-E-F-G-H
- A-B-D-F-G-H
- A-B-D-E-H
- A-C-E-H
c. How many weeks will it take to complete the project?
Number of weeks
d.Which activities have slack, and how much?
- E1 weekH3 weeks.
- B2 weeksD1 week.
- C5 weeksE1 week.
Use excel formulas, spreadsheet.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started