Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 4 C A 5 D B 4 E C D
Schedule the following activities using CPM:
ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
A | 3 | |
B | A | 4 |
C | A | 5 |
D | B | 4 |
E | C D | 8 |
F | D | 6 |
G | F | 4 |
H | E G | 5 |
b. What is the critical path?
multiple choice 1
A-C-E-F-G-H
A-B-E-H
A-B-D-F-G-H
A-B-D-E-H
c. How many weeks will it take to complete the project?
d. Which activities have slack, and how much?
multiple choice 2
E 1 week H 2 weeks.
C 5 weeks E 2 weeks.
B 1 week D 3 weeks.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started