Question

1 Approved Answer

Schedule the following activities using CPM: table [ [ ACTIVITY , IMMEDIATE PREDECESSOR,TIME ( WEEKS ) ] , [ A , - , 3

Schedule the following activities using CPM:
\table[[ACTIVITY,IMMEDIATE PREDECESSOR,TIME (WEEKS)],[A,-,3],[B,A,4],[C,A,9],[D,B,2],[E,C,D,7],[F,D,3],[G,F,4],[H,E,G,5]]
b. What is the critical path?
A-B-D-F-G-H
A-B-D-E-H
A-C-E-H
A-C-E-F-G-H
c. How many weeks will it take to complete the project?
Number of weeks
d. which activites have slack, and how much?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Processes and Supply Chains

Authors: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman

12th edition

134741064, 9780273766834, 027376683X, 9780273766940, 273766945, 9780273766841, 273766848, 978-0134741062

More Books

Students also viewed these General Management questions