Question: Schedule the project described in the following table, subject to a resource constraint of 16 men. Any man can work on any task. For a

Schedule the project described in the following table, subject to a resource constraint of 16 men. Any man can work on any task. For a given job, any crew size within, and including, the stated limits may be selected, if it is exactly divisible into the resource requirement. ( For example, job b requires 24 mandays. A crew size of 2, 3, 4, or 6 is permissable, but not 5 ). Crew sizes do not effect efficiency. The schedule length is to be minimized within the given resource LIMIT and keeping the technological constraints ( the ordering of Tasks) unaltered. Find the number of idle man-days.

Task

Immediate Predecessor

Resource Requirements

(man-days)

Range of Permissable Crew Sizes

Minimum

Maximum

A

--

45

5

15

B

A

24

2

6

C

A

96

4

12

D

A

50

2

10

E

D

30

2

10

F

C

60

4

12

G

C

12

1

6

H

B

35

5

7

I

F

42

3

14

J

G, E

24

3

8

K

I, J

20

2

10

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To plan the venture and limit the timetable length inside the asset imperative of 16 men we can foll... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!