Question: Schedule the project described in the following table, subject to a resource constraint of 16 men. Any man can work on any task. For a
Schedule the project described in the following table, subject to a resource constraint of 16 men. Any man can work on any task. For a given job, any crew size within, and including, the stated limits may be selected, if it is exactly divisible into the resource requirement. ( For example, job b requires 24 mandays. A crew size of 2, 3, 4, or 6 is permissable, but not 5 ). Crew sizes do not effect efficiency. The schedule length is to be minimized within the given resource LIMIT and keeping the technological constraints ( the ordering of Tasks) unaltered. Find the number of idle man-days.
Task | Immediate Predecessor | Resource Requirements (man-days) | Range of Permissable Crew Sizes | |
Minimum | Maximum | |||
A | -- | 45 | 5 | 15 |
B | A | 24 | 2 | 6 |
C | A | 96 | 4 | 12 |
D | A | 50 | 2 | 10 |
E | D | 30 | 2 | 10 |
F | C | 60 | 4 | 12 |
G | C | 12 | 1 | 6 |
H | B | 35 | 5 | 7 |
I | F | 42 | 3 | 14 |
J | G, E | 24 | 3 | 8 |
K | I, J | 20 | 2 | 10 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
To plan the venture and limit the timetable length inside the asset imperative of 16 men we can foll... View full answer
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock