Schedule-Cost-Resource The table below contains cost, resource, and schedule data for a hypothetical project. Questions: Create a network diagram for the tasks listed in the
- Schedule-Cost-Resource
The table below contains cost, resource, and schedule data for a hypothetical project.
Questions:
- Create a network diagram for the tasks listed in the table above.
- Calculate earliest start, latest start, and float for each task.
Task | Earliest start (ES) | Latest start (LS) | Float |
A | |||
B | |||
C | |||
D | |||
E | |||
F |
- Given the information captured in the network diagram, create a Gantt chart for the project. In the Gantt chart, picture weekends. (Assume the project begins on a Tuesday and that a week of effort is five working days long.)
- Calculate level of effort, labor costs, and total costs per task and put the values in the appropriate cells in the first table above.
- Assume the company being examined here has only two testers. How will this show up on a resource histogram? How should the work for Tasks D and E be leveled? What, if any, impact will the resource leveling have on the project duration?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started