Scheduling action taken after the critical path is established which adjusts start and finish dates based on resource constraints and can cause the critical path
Scheduling action taken after the critical path is established which adjusts start and finish dates based on resource constraints and can cause the critical path to change.
Group of answer choices
Smoothing
Leveling
Crashing
Fasttracking