Question

1 Approved Answer

Scheduling For an organization, the following project schedule is given. Assume that all times are in days. Task Predecessor Normal Time Crash Time Crash Cost

Scheduling

For an organization, the following project schedule is given. Assume that all times are in days.

Task Predecessor Normal Time Crash Time Crash Cost Slope
A None 7 7 NA
B A 3 3 NA
C A 8 4 600
D A 4 4 NA
E B 6 5 600
F C, D 2 2 NA
G E, F 6 6 NA
H F 5 3 400
I G, H 4 4 NA
J I 2 2 NA

In a 3 to 4 page Microsoft Word document, address the following:

  • Draw the AON project network using Microsoft Project, Microsoft Visio, or some other tool capable of creating such a network. Perform a critical path analysis for the network and calculate the ES, EF, LS, and LF times.
  • Calculate the slack time for each activity.
  • Identify the critical path.
  • Assume that the organization will receive a $400 bonus for each day the duration of the project is shortened. The organization is also responsible for paying the crash cost associated with shortening the schedule. To maximize the net profit, identify which task you should crash and by how much.

Support your responses with examples.

Cite any sources in APA format.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project management the managerial process

Authors: Eric W Larson, Clifford F. Gray

5th edition

73403342, 978-0073403342

More Books

Students also viewed these General Management questions

Question

Copy and complete the statement. 3800 m ? km =

Answered: 1 week ago

Question

7. Show that (E F)c = EcFc.

Answered: 1 week ago