Scope Statement Sample Project Name Project Number Project Manager Prioritization Owner(s) Statement of WorkProject Description and Project Product This section is typically a detailed amplification
Scope Statement Sample
Project Name | Project Number | ||
Project Manager | Prioritization | ||
Owner(s) |
Statement of WorkProject Description and Project Product | This section is typically a detailed amplification of the project SOW and mission from the project charter. This also includes how you intend to accomplish the project. "We intend to complete that... And here are the steps we intend to use to accomplish the project." This section is typically a detailed amplification of the SOW product description from the project charter. What will the product of the project look like, or what should it be able to do when completed? |
Project Deliverables | What are the tangible outputs or services of this project? What big-picture items will have to be created or performed in order to accomplish the statement of work? These are the deliverables to be found in the WBS. | |||
Project Objectives | What are the cost, schedule, and quality objectives of this project? | |||
Project Assumptions | What are the assumptions on which the project is based on? | |||
Project Constraints | What are the major limiting factors that affect the project? | |||
Exclusions | What are the boundaries of the project? What is to be included, and what is to be excluded from the project? | |||
Acceptance Criteria | What must the product be able to do when completed to be acceptable to the customer? What standards or regulations must the product meet? What performance specifications must the product meet to be acceptable to the customer? | |||
| ||||
Approvals | ||||
Type Name | Signature | Date | ||
Project Manager Approval: | ||||
Customer/Sponsor Approval: | ||||
Course Project Part 2Due Week 2(graded, 70 points) | |||
Assignment | Tasks | Deliverable(s) | Points |
Scope Statement |
| Project Scope (Word doc) | 10 points |
Detailed Resource Loaded Baseline WBS and Schedule |
Note: If your resources are leveled, there should be no unrealistically loaded resources. | MS Project file | 40 points |
Reports |
Overallocated Resource, Resource Overview reports, and the Cost Overview Report:
| Scope and budget balancing (Word doc) | 20 points |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started