Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Seasons Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments

Seasons Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1,550,000 each quarter. The total contract price is $18,600,000 and Seasons estimates total costs of $17,750,000. Seasons estimates that the building will take 3 years to complete, and commences construction on January 2, 2021. At the end of 2022, estimated total costs were $18,000,000.

Seasons Construction completes the remaining 25% of the building construction on December 31, 2023, as scheduled. At that time the total costs of construction are $18,750,000. What is the total amount of Revenue from Long-Term Contracts and Construction Expenses that Seasons will recognize for the year ended December 31, 2023?

Revenue = $4,687,500, Expense = $4,687,500

Revenue = $4,650,000, Expense = $5,250,000

Revenue = $4,650,000, Expense = $4,687,500

Revenue = $18,600,000, Expense = $18,750,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting and Reporting a Global Perspective

Authors: Michel Lebas, Herve Stolowy, Yuan Ding

4th edition

978-1408076866

Students also viewed these Accounting questions