Question

1 Approved Answer

Seasons Constructions is constructing an office building under contract for canon co & uses the % of completion method. The contract calls for progress billing

Seasons Constructions is constructing an office building under contract for canon co & uses the % of completion method. The contract calls for progress billing and payments of $1,550,000 each quarter. Total contract price is 18,600,000 and Seasons estimates costs of $17,750,000.Seasons estimates that the building will take 3 years to complete and will begin on Jan 2, 2018.

seasons construction completes the remaining 25% of the building construction on dec 31, 2020 as scheduled. at that time cost of construction are 18750000. what is the total amount of revenue from long term contracts and construction expenses that seasons will recognize for the year ended december 31, 2020

Please show step by step solutions - thank you

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles of Accounting

Authors: Needles, Powers, crosson

11th Edition

1439037744, 978-1133626985, 978-1439037744

More Books

Students also viewed these Accounting questions

Question

Explain the details of the purchasing power parity (PPP) theory.

Answered: 1 week ago

Question

What else could you do?

Answered: 1 week ago