Selected T-accounts of Moore Company are given below for the just completed year: Raw Materials Debit Credit Balance 1/1 30,000 Credits ? Debits 150,000 Balance
Selected T-accounts of Moore Company are given below for the just completed year:
Raw Materials | |||
---|---|---|---|
Debit | Credit | ||
Balance 1/1 | 30,000 | Credits | ? |
Debits | 150,000 | ||
Balance 12/31 | 40,000 |
Manufacturing Overhead | |||
---|---|---|---|
Debit | Credit | ||
Debits | 189,500 | Credits | ? |
Work in Process | |||
---|---|---|---|
Debit | Credit | ||
Balance 1/1 | 35,000 | Credits | 515,000 |
Direct materials | 105,000 | ||
Direct labor | 195,000 | ||
Overhead | 214,500 | ||
Balance 12/31 | ? |
Factory Wages Payable | |||
---|---|---|---|
Debit | Credit | ||
Debits | 215,000 | Balance 1/1 | 16,500 |
Credits | 210,000 | ||
Balance 12/31 | 11,500 |
Finished Goods | |||
---|---|---|---|
Debit | Credit | ||
Balance 1/1 | 55,000 | Credits | ? |
Debits | ? | ||
Balance 12/31 | 82,500 |
Cost of Goods Sold | |||
---|---|---|---|
Debit | Credit | ||
Debits | ? |
Required:
1. What was the cost of raw materials used in production during the year?
2. How much of the materials in (1) above consisted of indirect materials?
3. How much of the factory labor cost for the year consisted of indirect labor?
4. What was the cost of goods manufactured for the year?
5. What was the unadjusted cost of goods sold for the year? Do not include any underapplied or overapplied overhead in your answer.
6. If overhead is applied to production on the basis of direct labor cost, what predetermined overhead rate was in effect during the year?
7. Was manufacturing overhead underapplied or overapplied? By how much?
8. Compute the ending balance in Work in Process. Assume that this balance consists entirely of goods started during the year. If $11,750 of this balance is direct labor cost, how much of it is direct materials cost? Applied overhead cost?
Compute the ending balance in Work in Process. Assume that this balance consists entirely of goods started during the year. If $11,750 of this balance is direct labor cost, how much of it is direct materials cost? Applied overhead cost?
Ending balance in the work in process Direct materials cost Applied overhead costStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started