Session 9 Homework Problems 1. A cell phone manufacturer tests a sample of 100 units every day for quality control. The following list shows the
Session 9 Homework Problems
1. A cell phone manufacturer tests a sample of 100 units every day for quality control. The following list shows the number of defective units for the past 15 days. a. Create a control chart for this process and indicate if the process is in control. Day # of defective units 1 12 2 14 3 12 4 45 5 22 6 17 7 10 8 16 9 27 10 36 11 8 12 10 13 10 14 12 15 10