Sharon Glessing, controller for anyon Company, has noticed that the comparaces a 75 percent learning rate for its specially design fine in planning the cost of the latest design, Sharon assumed that the first set of units would take 1.000 direct labor hours. She decided to use this information in budgeting for the cost of the total project, which would involve the manufacture of 16 sets. Direct labor is paid $40 per hour Required: 1. Complete the table below showing results by row for total production of one un, two units, four units, elgt units, and sixteen units (Round hour answers to two significant digits.) (Round Cumulative Total Time answers to the nearest whole number.) Cumulative Number Cumulative Average Time Cumulative Total Times of Units per Unit in Hours Labor Hours 1 2 4 8 16 2. What is the total labor cost Janson Company makes eight sets? Steen? (Use the rounded answers in the subsequent computations) Total labor cost for eight sets Total labor cost for sixteen sets 3. Using the logarithmic function, complete the table below showing results by row for each of unit sets one through eight. (Round hour awwers to two wicant digits.) (Round Cumulative Total Time and Time for Last Unit answers to the nearest whole number) Cumulative Number Cumulative Average Time Cumulative Total Timer Time for of Units per Unit in Hours Labor Hours Last Unit TI 2. What is the total labor conson Company makes it was wees? Use the rounded wwers in the subsequent companions) Total labor cost for eight sets Total labor cost for when 3. Using the logarifunction, complete the table below showing results by row for each of use one through eight (Roundhour answers to two cats) (Round Cumulative Total Time and Time for Last Unswers to the nearest whole number) Cumulative Number Cumulative Average Time Cumulative Total Time Time for of Uw per Un in Hours Labor Hours Last Unit 2 4 What is the direct labor cost for the inte