Sheffield has a standard of 1.5 pounds of materials per unit, at $6 per pound. In producing 2000 units, Sheffield used 3200 pounds of materials
Sheffield has a standard of 1.5 pounds of materials per unit, at $6 per pound. In producing 2000 units, Sheffield used 3200 pounds of materials at a total cost of $18720. Sheffield's total variance is
| $900 F. |
| $1200 U. |
| $480 U. |
| $720 U. |