Sheridan Enterprises Ltd. has entered into a contract beginning in February 2020 to build two warehouses for Atlantis Structures Ltd. The contract is a non-cancellable

image text in transcribed
Sheridan Enterprises Ltd. has entered into a contract beginning in February 2020 to build two warehouses for Atlantis Structures Ltd. The contract is a non-cancellable fixed price contract for $10.2 million. The following data pertain to the construction period. Costs for the year Estimated costs to complete Progress billings for the year (non-refundable) Cash collected for the year 2020 $4,005,000 4,895,000 3,680,000 3.245.000 2021 4,895,000 1.100.000 4,320,000 4,370,000 2022 1,000,000 -0- 2,200,000 2.585.000 Using the percentage of completion method, calculate the percent complete for each year of the contract 2020 2021 2022 Percent complete 90 % List of Accounts

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting

Authors: Walter B. Meigs, A. N. Mosich, Robert F. Meigs

2nd Edition

0070412901, 978-0070412903

More Books

Students also viewed these Accounting questions

Question

2. What role should job descriptions play in training at Apex?

Answered: 1 week ago