Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

SHOW HOW TO DO IT IN EXCEL AAA Investment Fund has a solar energy project under evaluation. The initial investment of this project includes land

SHOW HOW TO DO IT IN EXCEL AAA Investment Fund has a solar energy project under evaluation. The initial investment of this project includes land purchase and a solar energy generating system. AAA Investment Fund has no plan to operate it forever. Their strategy is to set up the energy plant and sell the energy to the spot market as a long-term project. As a financial analyst of AAA Investment Fund, your manager asked you to evaluate the project, and offer advice on which solar panel system they should adopt. The detailed information is as below: 1. Project life is 25 years. 2. Land cost $6 million. The land is expected to appreciate by 2% per year over 25 years. Assume your cost of land is a fair market value and you are expected to sell the land at fair market value by the end of 25 years. 3. You have a choice of choosing fixed solar panels or rotating solar panel systems. 1 MWh (1000 kW per hour) system of rotating panel systems costs $1.45 million. Your purchased land allows you to build a 25MWh system. A rotating solar system is more efficient in producing solar energy with an average output of 5.6 hours per day. The maintenance cost is about 10% of the sales revenue. 4. If you use fixed solar panel systems. 1MWh (1000 kW per hour) system costs $1.2 million. You can build a 30MWh system as the fixed systems require less space. However, the effective output from the average daily sunshine is about 4.5 hours. The maintenance cost is about 8% of the sales revenue. 5. You can sell your electricity to the spot market at price of $100 per MWh in the first three years and then the price will increase by $4 every three years. You will also get a government bonus of $80 per MWh (e.g, Large-Scale Generation Certificate) for the first 5 years. 6. After 25 years, it will cost you $60,000 to clean the site. 7. Additional assumptions: - The discount rate for the project is 10%. - The tax rate is constant at 30%. Capital gains tax is 15% for land sales after 25 years (50% discount of the normal tax rate). - Straight line depreciation of solar panel system. - 365 days per year. - Both systems will lose 0.75% efficiency per year. - The project requires $100,000 working capital for liquidity purpose (It will be refunded fully by the end of project). - Please see more details in the excel file. image text in transcribed

\begin{tabular}{|c|c|c|} \hline \multicolumn{3}{|l|}{ Key inputs } \\ \hline Project life & 25y & years \\ \hline Land cost & 600000 & $ \\ \hline Land appreciation rate & 2.00% & p.a \\ \hline Sale price per MWh & 100 & $ \\ \hline Price increase per 3 years & & $ \\ \hline First 5 year gov rebate per MWh & 80 & $ \\ \hline Cleaning cost by the end of proj, & 60000 & \\ \hline Discount rate for the project & 10% & p.a \\ \hline Tax & 30% & \\ \hline Discounted capital gain tax & 15% & \\ \hline Days per year & 365 & \\ \hline Efficiency lose yearly & 0.75% & p.a \\ \hline Working capital required & 100000 & $ \\ \hline \multicolumn{3}{|c|}{ Solar Panel System } \\ \hline \multicolumn{3}{|l|}{ Rotating system } \\ \hline Installation cost per MWh & 1450000 & $ \\ \hline Total installed capacity & 25 & MWh \\ \hline Effective hours per day & 5.6 & \\ \hline cost percentage of sales & 10% & \\ \hline depreciation & straight line over 25y & years \\ \hline Salvage value in 25 years & 12000 & $ \\ \hline \multicolumn{3}{|l|}{ Fixed system } \\ \hline Installation cost per MWh & 1200000 & $ \\ \hline Total installed capacity & 30n & MWh \\ \hline Effective hours per day & 4.5 & \\ \hline cost percentage of sales & 8% & \\ \hline depreciation & straight line over 25y & years \\ \hline Salvage value in 25 years & 10000 & $ \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Management Principles and Application

Authors: Arthur J. Keown, J. William Petty, David F. Scott, Jr.

10th edition

536514119, 536514110, 978-0536514110

More Books

Students also viewed these Finance questions