Simon is the owner of a table-building store in New Jersey. Four (4) workers perform three (3) steps in the manufacturing process. Each workerreceives EUR

Simon is the owner of a table-building store in New Jersey. Four (4) workers perform three (3) steps in the manufacturing process. Each workerreceives EUR 50,- per hour.

Step 1: The required pieces for the tables are loaded into a spraying machine which is operated by one (1) worker. Spraying takes 4 minutes for the pieces needed for one table.

Step 2: The second worker receives the pieces and applies a protective finish. This step requires 5 minutes for all pieces needed for one table.

Step 3: Two workers assemble the tables. They work at the same time on different tables and assembly takes a total of 9 minutes per chair.

What is the cycle time? What is the bottleneck?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Statistics For Managers Using Microsoft Excel

Authors: David M. Levine, David F. Stephan, Kathryn A. Szabat

7th Edition

978-0133061819, 133061817, 978-0133130805

More Books

Students also viewed these General Management questions