Simulation 1 - Project Management Suppose that a software development project team has arrived at the following time estimates for a software project. a .

Simulation 1- Project Management
Suppose that a software
development project team has
arrived at the following time
estimates for a software project.
a. The duration of each task is described by a normal statistical
distribution. If the duration of each task was precisely the mean of this
distribution, what would the duration of the project be?
b. Report the overall mean duration of the project from 300 simulations of
the above model (using the statistical distributions and SimQuick).How does this number compare with the duration reported in part a?
Project duration =(1 mean inventory of End)*(Simulation duration)
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Stage Management

Authors: Lawrence Stern

8th Edition

0205449735, 978-0205449736

More Books

Students also viewed these General Management questions

Question

Evaluate possible explanations of the functions of sleep.

Answered: 1 week ago