Question
Sinar Sdn Bhd (SSB) manufactures and sells two types of automobile batteries, the Heavy Duty (HD) and the Long Life (LL). Each unit of battery
Sinar Sdn Bhd (SSB) manufactures and sells two types of automobile batteries, the Heavy Duty (HD) and the Long Life (LL). Each unit of battery consumes two types of material, M1 and M2.SSB is preparing its annual budget for the year ending December 31, 2019. The Assistant Accountant provides the following data:
Product
HD
Product
LL
Sales budget:
Sales revenue
RM9,000,000
RM4,800,000
Unit selling price
RM20.00
RM30.00
Production budget:
Beginning inventory finished goods
20,000 units
10,000 units
Direct labour budget:
Direct Labour time per unit
0.4 hr
0.6 hr
Direct labour rate per hour
RM10.00
RM10.00
Direct material Budget:
M1 - RM2.00 per kg
2 kg
3kg
M2 - RM3.00 per kg
2.5 kg
4 kg
Beginning direct Material:
M1 - 500,000kg
M2 - 300,000kg
Additional information:
Ending inventory for finished products will be 10% higher than its beginning inventory and ending inventory for materials will be 20% lower than its beginning inventory.
Required:
a)Prepare production budget for each product.(10 marks)
b)Prepare Material purchases budget (M1 and M2).(14 marks)
Prepare direct labour budget for each product.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started