Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $123,520. Overhead is
Single plantwide factory overhead rate
Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $123,520. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit:
Budgeted Production Volume | Direct Labor Hours Per Unit | ||||
Flutes | 2,400 | units | 0.5 | ||
Clarinets | 800 | 1.4 | |||
Oboes | 1,400 | 1.1 |
If required, round all per unit answers to the nearest cent.
a. Determine the single plantwide overhead rate. $fill in the blank 1 per direct labor hour
b. Use the overhead rate in (a) to determine the amount of total and per-unit overhead allocated to each of the three products.
Total Factory Overhead Cost | Per Unit Factory Overhead Cost | |
Flutes | $fill in the blank 2 | $fill in the blank 3 |
Clarinets | fill in the blank 4 | fill in the blank 5 |
Oboes | fill in the blank 6 | fill in the blank 7 |
Total | $fill in the blank 8 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started