Smith Corporation is considering the implementation of a JIT inventory system. The company recently analyzed its cycle time to determine the average number of days

Smith Corporation is considering the implementation of a JIT inventory system. The company recently analyzed its cycle time to determine the average number of days spent in each activity of its production process.

Production ActivityNumber of days

Receiving materials1

Inspecting materials4

Storing materials 9

Moving materials intro production 6

Setting up production equipment 7

Cutting materials6

Assembling materials7

Packaging finished products 4

Packaging finished products 1

a.What steps are needed to determine the value-adding production activities?

b.What is the total cycle time in days?

c.What is the manufacturing efficiency ratio______%?

d.Discuss the activities that might be reduced or eliminated to implement an efficient JIT system?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting Fundamentals With Connect Plus

Authors: John Wild

4th Edition

77785932, 978-0077785932

More Books

Students also viewed these Accounting questions

Question

4. What is the goal of the others in the network?

Answered: 1 week ago

Question

2. What we can learn from the past

Answered: 1 week ago