Sodaco runs a plant that makes and bottles private label soft drinks, sold directly to retailers. One client has recently placed an order for one
Sodaco runs a plant that makes and bottles private label soft drinks, sold directly to retailers. One client has recently placed an order for one of the SKU's with the following delivery schedule over the next ten weeks (one period=one week):
PERIOD DEMAND
1 3000
2 3100
3 3200
4 3100
5 2900
6 2800
7 2800
8 2900
9 2800
10 3000
The order is of one-time character - there are no promises for future orders from the same client.
Sodaco needs your help to develop a production plan that minimizes the total costs. Costs are incurred both from holding inventory of finished goods and from changeovers in the production line. Sodaco estimates these costs according to the following:
- Inventory holding costs: $0.1 per itemand week
- Production setup costs: $800 per production run
Any products delivered in the same week as manufactured incur no holding costs. Holding costs are then incurred for every week after the manufacturing week. Capacity is not an issue at this point.
The Silver-Meal heuristic provides a slightly more advanced way to develop a production schedule.
Using the Silver-Meal heuristic, what is the total cost for producing the ordered units?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
To calculate the total cost for producing the ordered units using the SilverMeal heuristic we will f...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started