Question
Software Ltd has established a project team to undertake some important market research work. It is possible to reduce the expected or normal times for
Software Ltd has established a project team to undertake some important market research work. It is possible to reduce the expected or normal times for certain activities in units of one week (but not in fractions of a week) but at an extra cost. The relevant information is given below.
Activity | Predecessor | Normal Time (weeks) | Normal Cost ($) | Crash Time (weeks) | Crash Cost ($) |
A |
| 5 | 4000 | 3 | 6000 |
B |
| 4 | 3000 | 4 | 3000 |
C | A | 2 | 6000 | 1 | 21000 |
D | C | 4 | 1000 | 4 | 1000 |
E | B | 5 | 4000 | 3 | 7000 |
F | B | 5 | 7000 | 1 | 14000 |
G | B, C | 4 | 4000 | 2 | 24000 |
H | F | 3 | 5000 | 2 | 15000 |
In addition to the costs shown there is a cost of retainer fees and administration overheads of $10000 for each week that the project lasts.
a) What is the normal expected duration of the project? What is the critical path?
The normal expected duration of the project is: | Answer |
---|---|
The critical path is: | Answer |
b) What would be the cost of completing the project using the normal durations?
c) What would be the duration of the project if costs are to be minimized?
Activity | Maximum Crash Time (weeks) | Crash Cost/week |
A | Answer | Answer |
B | Answer | Answer |
C | Answer | Answer |
D | Answer | Answer |
E | Answer | Answer |
F | Answer | Answer |
G | Answer | Answer |
H | Answer | Answer |
Stage | Crash Activity | Time Reduction (weeks) | Resulting Critical Path(s) | Project Duration (weeks) | Project Direct Costs ($) | Crash Cost ($) | Total Indirect Costs ($) | Total Project Costs ($) |
0 |
|
|
|
|
|
|
|
|
1 |
|
|
|
|
|
|
|
|
2 |
|
|
|
|
|
|
|
|
Therefore the optimal project duration is .. weeks, and the optimal project cost is $ ..........
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started