Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Software Ltd has established a project team to undertake some important market research work. It is possible to reduce the expected or normal times for

Software Ltd has established a project team to undertake some important market research work. It is possible to reduce the expected or normal times for certain activities in units of one week (but not in fractions of a week) but at an extra cost. The relevant information is given below.

Activity

Predecessor

Normal Time (weeks)

Normal Cost ($)

Crash Time (weeks)

Crash Cost ($)

A

5

4000

3

6000

B

4

3000

4

3000

C

A

2

6000

1

21000

D

C

4

1000

4

1000

E

B

5

4000

3

7000

F

B

5

7000

1

14000

G

B, C

4

4000

2

24000

H

F

3

5000

2

15000

In addition to the costs shown there is a cost of retainer fees and administration overheads of $10000 for each week that the project lasts.

a) What is the normal expected duration of the project? What is the critical path?

The normal expected duration of the project is: Answer
The critical path is: Answer

b) What would be the cost of completing the project using the normal durations?

c) What would be the duration of the project if costs are to be minimized?

Activity

Maximum Crash Time (weeks)

Crash Cost/week

A

Answer

Answer

B

Answer

Answer

C

Answer

Answer

D

Answer

Answer

E

Answer

Answer

F

Answer

Answer

G

Answer

Answer

H

Answer

Answer

Stage

Crash Activity

Time Reduction (weeks)

Resulting Critical Path(s)

Project Duration (weeks)

Project Direct Costs ($)

Crash Cost ($)

Total Indirect Costs ($)

Total Project Costs ($)

0

1

2

Therefore the optimal project duration is .. weeks, and the optimal project cost is $ ..........

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Efficient Auditing Of Private Companies A Guide To Audit Planning Implementation And Control

Authors: The Institute Of Chartered Accountants

1st Edition

1841400432, 978-1841400433

More Books

Students also viewed these Accounting questions

Question

Learn how to conduct experiments with more than two groups

Answered: 1 week ago

Question

socialist egalitarianism which resulted in wage levelling;

Answered: 1 week ago

Question

soyuznye (all-Union, controlling enterprises directly from Moscow);

Answered: 1 week ago