SOLUTION OF NETWORK ANALYSIS PROBLEM 3 COMPLETE THE TABLE BELOW. 2 . DRAW A BAR CHART SHOWING ALL ACTIVITIES AT EARLIEST START DATES. 3 .

SOLUTION OF NETWORK ANALYSIS PROBLEM 3
COMPLETE THE TABLE BELOW.
2. DRAW A BAR CHART SHOWING ALL ACTIVITIES AT EARLIEST START DATES.
3. FROM THE BAR CHART SHOW THE RESOURCE REQUIREMENTS IN THE FORM OF A HISTOGRAM.
\table[[\table[[ACTIV.],[EVENT],[NOS.]],DURATION,EARLIEST,LATEST,FLOAT],[START,FINISH,START,FINISH,TOTAL,FREE,INDEPENDENT],[1-2,6,,,,,,,],[1-3,5,,,,,,,],[1-5,2,,,,,,,],[2-7,4,,,,,,,],[3-4,6,,,,,,,],[4-7,0,,,,,,,],[4-10,3,,,,,,,],[5-6,3,,,,,,,],[6-8,7,,,,,,,],[6-9,2,,,,,,,],[7-9,4,,,,,,,],[7-10,2,,,,,,,],[8-9,2,,,,,,,],[9-10,5,,,,,,,]]
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Sustainability And Supply Chain Management

Authors: Jay Heizer, Barry Render, Chuck Munson, Paul Griffin

3rd Canadian Edition

0134838076, 978-0134838076

More Books

Students also viewed these General Management questions